CONST. OF ECDE CENTRE AT NYAISA PRI. SCH. NYCG/Q259/2015-2016 On-Going 3,207,311.26 Manga Feedback
MATERNITY BLOCK AT KIANUNGU HEALTH FACILITY NYCG/Q118/2014-2015 Improved infrustructure Completed 3,994,261.60 Bosamaro Feedback
COMPLETION OF LABORATORY BLOCK AT MANGA SUB-COUNTY DIST. HOSPITAL NYCG/Q050/2015 - 2016 Completed 2,209,742.00 Manga Feedback
REPAIR AND MAINTANANCE OF NYAIKURO JUNCTION- GESURE ROAD NYCG/KRB/Q328/2015-2016 Completed 2,094,304.60 Manga Feedback
MOTOR CYCLE SHADE AT TOMBE MKT NYCG/Q021/2015-2016 Completed Manga Feedback
MOTOR CYCLE SHADE AT MANGA NYCG/Q021/2015-2016 Completed Manga Feedback